Our Process (Timeline)
- Day 0–3: Site survey → design & brand selection → 10% booking.
- Day 4–14: Drawings, DISCOM application, structure fabrication.
- Day 15–25: Material readiness → 85% milestone → dispatch & delivery.
- Day 26–35: Installation, testing, documentation.
- Day 36–60: Net meter exchange (DISCOM) → final checks → 5% handover.